Hi-Land Acres Water and Sanitation District Sewer Collection System Condition Assessment and Rehabilitation Project
Brighton, CO
Hi-Land
Acres Water and Sanitation District serves 115 residential customers
with 56 manholes.
Bai Engineers worked as prime and performed sewer manhole and pipeline
CCTV record review for sewer collection system condition assessment.
Several field inspections and condition assessment for the existing
wastewater collection system were completed in September 2018. All
manholes and pipelines were surveyed and rated based on Government
Accounting Standards Board Statement 34 (GASB34). A list of pipes that
needed rehabilitation was documented. Bai Engineers is currently
managing the district wide sewer pipe rehabilitation project using the
Cured-In-Place-Pipe (CIPP) technique.